Combined service of setting up of Wet Limestone FGD plant & its operation & maintenance not a composite supply

Combined service of setting up of Wet Limestone FGD plant & its operation & maintenance not a composite supply

Deepak Gupta | Jan 3, 2022 |

Combined service of setting up of Wet Limestone FGD plant & its operation & maintenance not a composite supply

Combined service of setting up of Wet Limestone FGD plant & its operation & maintenance not a composite supply

It was submitted by the applicant that his activity shall be considered as composite supply of setting up of plant and operation and maintenance with setting up of plant as principal supply.

Authority of Advance Ruling noticed that supply of operation & maintenance service started only on completion & handing over of the operating FGD plant integrated with the existing power plant and subject to the fulfillment of performance guarantees. This clearly indicates that the setting up of the FGD plant and the O&M of the same are two separate distinguished supplies and the supply of O&M service starts after completion of the setting up of the FGD plant. Thus these two supplies are not naturally bundled.

Further, it was observed that the Contract provides for a price break up and not only from the price break up but also from the terms and conditions of the agreement show that the activities of operation & maintenance are separately identified.

The Authority concluded that setting up of FGD plant attracts GST at the rate of 12%. Further the Operation & Maintenance of the FGD plant merit classification under SAC 9985, as “Business Support” service and attracts CST at the rate of 18%.

StudyCafe Membership

Join StudyCafe Membership. For More details about Membership Click Join Membership Button
Join Membership

In case of any Doubt regarding Membership you can mail us at [email protected]

Join Studycafe's WhatsApp Group or Telegram Channel for Latest Updates on Government Job, Sarkari Naukri, Private Jobs, Income Tax, GST, Companies Act, Judgements and CA, CS, ICWA, and MUCH MORE!"




Author Bio
My Recent Articles
ROC Imposes Penalty for 2-Day MGT-15 Filing Delay; Company Blames MCA Portal Glitches ICAI revises Eligibility Criteria for Empanelment to Impart Industrial Training HC Extends GST Amnesty to Early GSTR-9 Filers; Sets Aside General Penalty Where Late Fee Is Paid GSTR-9, 9C Mandatory vs Optional Tables For FY 2024-25 CA cannot be Held for money laundering for merely issuing Income Tax Form 15CB: Supreme CourtView All Posts